← All projects Shift & workforce planning · Atlas Honda

Assembly Shift, Overtime & Transport Optimisation

Two assembly lines, one van fleet. How could the two-shift line take on overtime without extra van runs or a fatigue-heavy night?

Shift optimisationWorkforce planningTransportCost-benefit
2assembly lines planned together
2shifts share Line 2’s overtime
5options compared
Same fleetevery run used both ways
Recreated proposal slide showing both lines and the shared van runs, with illustrative timingsOpen full image ↗

The challenge

At Atlas Honda there were two motorcycle assembly lines on different shift patterns. Line 1 ran a single day shift. Line 2 ran two shifts back to back: a day shift, then a night shift that started as the day shift ended. Both lines relied on the same contracted transport vans.

Overtime caused two separate problems:

  • Extra van runs. On overtime days Line 1 stayed on past its normal finish, but Line 2’s day shift still left at the normal time. That meant one set of van runs for Line 2 at the normal finish and another for Line 1 when its overtime ended.
  • Line 2 couldn’t take overtime. A normal-length extension on the night shift finished at a time the vans couldn’t serve: they couldn’t take the night team home and still be back for the morning shift start. The only extension that matched the morning vans was much longer than the usual overtime block, and that wasn’t workable because of fatigue.

Adding vans would have fixed the transport side at a recurring cost, but not the fatigue. The question was whether rescheduling could fix both.

Mapping the constraint

I laid the two lines’ shift patterns and the van cycle side by side rather than treating transport as a separate problem:

PipelineLine 1 shift + overtime→Line 2 day shift→Line 2 night shift→Van runs out and back→Morning shift start

Together they showed the waste: van runs at different times for teams that could have travelled together, and a night-shift finish that never lined up with a van arrival.

Five options compared

OptionWhat it gets rightWhat goes wrong
No overtime on Line 2SimplestLine 2’s extra output is lost
Normal overtime on the night shiftUsual overtime lengthFinish doesn’t match the vans, so the morning pickup can’t be met
Long overtime on the night shiftFinish matches the morning vansToo long for one team: fatigue, safety and quality risk
Add van runsOperationally simpleRecurring cost, and the two lines still travel separately
Split Line 2’s overtime and align it with Line 1Overtime on both lines with the existing fleetThe night shift reports later on overtime days, so it needs clear communication

The proposed configuration

Line 1 kept its normal overtime pattern. On Line 2, I split the overtime between the two shifts and moved the changeover to Line 1’s overtime finish:

PipelineLine 2 day shift stays on until Line 1 finishes→Both lines go home on the same vans→Those vans bring the night shift in→Night shift runs until the morning shift starts→Morning vans take the night shift home

Each Line 2 team works part of the overtime instead of one team carrying all of it, and every van movement serves two groups on the same routes: the run that takes both day teams home brings the night shift in, and the run that brings the morning shift in takes the night shift home.

Why it balanced better

  1. Line 2 can take overtimeIts extra output was previously blocked by the van cycle.
  2. Fatigue kept in checkNo team works the long block; each shift carries a share.
  3. Fewer van runsLine 1 and Line 2’s day shift go home together instead of on separate runs.
  4. No extra fleetEvery run carries a team in both directions, so the existing vans and routes cover the new pattern.

Presentation and outcome

I turned the analysis into a cost-benefit proposal and presented it to senior plant leadership. It showed both problems could be solved by retiming Line 2’s changeover rather than adding vans, and it named the main implementation risk: the night shift’s later reporting time on overtime days needs clear communication and schedule discipline.

Of the options assessed, splitting Line 2’s overtime and aligning it with Line 1 gave the best balance of output, fatigue and transport cost.

Shift times, overtime hours, transport routes, fleet sizes and costs are internal and not published here. The screenshot is a recreation with illustrative data, not the original file.

Planning should turn complexity into action.

Open to Production Planner, Materials Planner, Production Controller and Supply Chain Planning roles in the UK.

ContactStraight to my inbox

Send me a message

I’ll reply to the email address you give here.